Road Resurfacing Update

Road resurfacing work will start on Saturday, September 16th and should finish on Monday, September 25th. They will be working Monday – Saturday.

Hours:

  • Monday - Friday: 7:00 am – 7:00 pm
  • Saturday: 9:00 am – 7:00 pm
  • Sunday: No Work will happen.

They will start with milling sections 9, 8, & 6 and will be removing up to 4” of asphalt in these areas. Please drive with caution in these areas.

Paving will start on September 19th. As of now, the paving will happen in the following order: 9, 8, 7, 6, 5, 4, 2, 1, 3.

**All of this is subject to change**

Thank you in advance for any inconvenience that this might cause.

Please contact the Street Department with any questions or concerns.